Feasibility of Options .... 4 months
-
Conventional Septic Feasibility .... 2 months
-
Soil Science & Preliminary Engineering
.....
7 months
-
DHEC Approval of PER .... 2 months
-
DHEC Issuance of Land Application Permit
....
7 months
-
DHEC Issuance of Permit-to-Construct .... 4 months
-
Total Duration through Permitting .... 20 months
Photo by AQWA, Inc.
-
School population = 1,060 students
-
Avg. Design Flow = 15,900 GPD
-
20,000 gal Septic & EQ Tanks
-
3,000 gal De-Nitrification Tank
-
12,000 gal Recirculation Tank
-
4-AX100 AdVantex Packed-Bed Textile Filters
-
Chlorine Disinfection
-
250,00 gal Treated Effluent Storage Tank
-
6-Acre, Multi-Zone Surface-Drip Irrigation
-
Construction Cost Opinion = $1.0 Million.
-
Challenge: 5 miles to nearest public sewer and site not
suitable for conventional septic system.
Solution: Advanced treatment with on-site drip-disposal in
wooded, un-developable area of site.
-
Challenge: Owner needed an acceptable wastewater disposal
solution to obtain State/OSF approval to proceed with school
design & construction on tight schedule.
Solution: Obtained quick approval of PER from DHEC to
satisfy SC Office of School Facilities and meet schedule.
The project was permitted for construction by DHEC in June
2006. Construction is scheduled to begin in September and be
completed by December 2006. |