Caliber Engineering Project News July, 2006

NEW RALPH CHANDLER
MIDDLE SCHOOL

SCHOOL DISTRICT OF GREENVILLE COUNTY, SC

NEW ON-SITE WASTEWATER SYSTEM

“1st DHEC CONSTRUCTION PERMIT IN SC”



 

 

 

 

 


PROJECT TIMELINE:

  • Feasibility of Options .... 4 months

  • Conventional Septic Feasibility .... 2 months

  • Soil Science & Preliminary Engineering ..... 7 months

  • DHEC Approval of PER .... 2 months

  • DHEC Issuance of Land Application Permit .... 7 months

  • DHEC Issuance of Permit-to-Construct .... 4 months

  • Total Duration through Permitting .... 20 months


Photo by AQWA, Inc.

PROJECT STATS:

  • School population = 1,060 students

  • Avg. Design Flow = 15,900 GPD

  • 20,000 gal Septic & EQ Tanks

  • 3,000 gal De-Nitrification Tank

  • 12,000 gal Recirculation Tank

  • 4-AX100 AdVantex Packed-Bed Textile Filters

  • Chlorine Disinfection

  • 250,00 gal Treated Effluent Storage Tank

  • 6-Acre, Multi-Zone Surface-Drip Irrigation

  • Construction Cost Opinion = $1.0 Million.

PROJECT HURDLES:

  1. Challenge: 5 miles to nearest public sewer and site not suitable for conventional septic system.

    Solution: Advanced treatment with on-site drip-disposal in wooded, un-developable area of site.
     

  2. Challenge: Owner needed an acceptable wastewater disposal solution to obtain State/OSF approval to proceed with school design & construction on tight schedule.

    Solution: Obtained quick approval of PER from DHEC to satisfy SC Office of School Facilities and meet schedule.

RESULTS:

The project was permitted for construction by DHEC in June 2006. Construction is scheduled to begin in September and be completed by December 2006.